SPECIFICATION SHEET β€’ SI METRIC
CAT: THERMO

Boiler Blowdown Rate

Estimate continuous boiler blowdown flow, blowdown percentage, and required feedwater from steam production and cycles of concentration.

OPERATING LIMITS β€” Boiler-water mass-balance calculation only; verify cycles definition, chemistry limits, intermittent versus continuous blowdown, condensate return, heat recovery, and operating procedures.
INPUT DESIGN PARAMETERS (SI)
kg/h
cycles
CALCULATED SPECIFICATION OUTPUT
Continuous Blowdown Rate
555.6 kg/h
Blowdown as Percent of Steam11.11 %
Approximate Feedwater Rate5555.6 kg/h

Technical Methodology & Engineering Principles

GOVERNING EQUATION
Blowdown fraction = 1 / (cycles βˆ’ 1); blowdown flow = steam production Γ— blowdown fraction; feedwater = steam + blowdown.
Assumptions & Scope

Steady-state mass balance with cycles defined as boiler-water concentration divided by feedwater concentration. Include surface blowdown, bottom blowdown, intermittent schedules, condensate return, and heat recovery separately.

Operating Range & Boundary

Use finite, physically meaningful inputs within the stated operating assumptions.