Open-Pit Stripping Ratio Calculator
Calculate volumetric (m³/m³) and mass (t/t) stripping ratios for open-pit mine planning.
💡 Engineering Knowledge PrimerOpen-pit stripping ratio compares waste overburden volume or tonnage moved per unit of economic ore extracted. Lower stripping ratios indicate higher open-pit mining profitability.
CALCULATION SCOPE — Deterministic calculation within the published assumptions. Independently verify all design decisions and project-specific code requirements.
Quick-Fill Material Presets
INPUT DESIGN PARAMETERS (SI)
m³
m³
t/m³
t/m³
CALCULATED SPECIFICATION OUTPUT
Mass Stripping Ratio (Waste:Ore)
✨4.46 t/t
| Volumetric Stripping Ratio | 5 m³/m³ |
| Total Material Moved | 15300000 t |
Related planning checklists
This calculator appears in the following engineering planning checklists:
Open-Pit Mine Planning
Mining Engineer1. Rock Quality Designation (RQD) & RMR Index2. Open-Pit Stripping Ratio Calculator3. Stockpile Volume & Tonnage Calculator
Technical Methodology & Engineering Principles
GOVERNING EQUATION
Mass Stripping Ratio = (Waste Volume × Waste Density) / (Ore Volume × Ore Density)
Assumptions & Scope
Uniform density over pit block model.
Operating Range & Boundary
Use finite, physically meaningful inputs within the stated operating assumptions.
Peer Reference: SME Mining Engineering Handbook (3rd ed.), Chapter 9.