Complete mass balance from slurry density through to concentrate and tailings production.
Use as a checklist, not an automated design workflow. Complete and verify each calculation independently. Only explicit carry-forward links move a compatible value; all other inputs remain your responsibility.
What this workflow covers
Complete mass balance from slurry density through to concentrate and tailings production.
This 4-step checklist is intended for process engineer. Confirm each linked calculator's units, formula, assumptions and operating limits before using the result in a project decision.
Checklist progress0 of 4 steps checked
Sequence Execution
1
Slurry Density & Concentration
Calculate slurry bulk density, specific gravity, percent solids by weight (Cw), and percent solids by volume (Cv).
WORKFLOW INSTRUCTION:Confirm the published assumptions, enter the project data, and record the result and operating limits for Slurry Density & Concentration.
2
Two-Product Mass Balance
Calculate concentrate recovery, yield, and stream mass flow rates from feed (f), concentrate (c), and tailings (t) assays.
WORKFLOW INSTRUCTION:Confirm the published assumptions, enter the project data, and record the result and operating limits for Two-Product Mass Balance.
3
Grade & Recovery Balance Check
Scope-limited calculation
Check mass pull and separation efficiency using a measured recovery at the selected concentrate grade.
WORKFLOW INSTRUCTION:Confirm the published assumptions, enter the project data, and record the result and operating limits for Grade & Recovery Balance Check.
4
Concentrate & Tailings Production Rate
Determine daily, monthly, and annual concentrate and tailings solids tonnages from plant feed capacity.
WORKFLOW INSTRUCTION:Confirm the published assumptions, enter the project data, and record the result and operating limits for Concentrate & Tailings Production Rate.